Overview of the Challenges in the Construction of Multistorey Reinforced Concrete Structure

Overview of the Challenges in the Construction of Multistorey Reinforced Concrete Structure

  IJETT-book-cover           
  
© 2022 by IJETT Journal
Volume-70 Issue-7
Year of Publication : 2022
Authors : Arti Sahu, S. Shanmugapriya
DOI : 10.14445/22315381/IJETT-V70I7P222

How to Cite?

Arti Sahu, S. Shanmugapriya, "Overview of the Challenges in the Construction of Multistorey Reinforced Concrete Structure" International Journal of Engineering Trends and Technology, vol. 70, no. 7, pp. 212-219, 2022. Crossref, https://doi.org/10.14445/22315381/IJETT-V70I7P222

Abstract
Reinforced Concrete multistory building construction can be speedup by using sequential floor construction. Builders' demands to remove formwork more quickly have resulted in building collapse. Sequential floor construction involves casting new slabs at a higher level before the lower floors attain their ultimate strength. Shores either completely or partially support the lower floors in this process. Therefore, the correct formwork stripping sequence and understanding of the early loading concept of concrete are required to perform this technique properly. Engaging the available advancements in this technique, such as construction methods, concrete strength advancement, and formwork systems, saves the project's time and cost. In response to the growing demand in the community for this information on new developments, limitations, and the application of construction techniques, this paper was conceived. Researchers can learn more about building construction, and professionals can keep up to date on the latest developments. Building designers and construction professionals may benefit from the paper's findings by refining their current methods and procedures.

Keywords
Construction techniques, Formwork, Load distribution, Reshoring, Successive floor construction.

Reference
[1] A. V. Kiyanets, “Resource-saving Construction Technologies,” Procedia Eng., vol. 150, pp. 2124–2127, 2016, doi: 10.1016/j.proeng.2016.07.251.
[2] D. Simavorian, J. de Brito, L. Castro, and M. Azenha, “Analysis of the effect of shoring on the behaviour of reinforced concrete slabs,” Constr. Build. Mater., vol. 143, pp. 473–489, 2017, doi: 10.1016/j.conbuildmat.2017.03.096.
[3] M. Benaicha, Y. Burtschell, and A. H. Alaoui, “Prediction of compressive strength at early age of concrete - Application of maturity,” J. Build. Eng., vol. 6, pp. 119–125, 2016, doi: 10.1016/j.jobe.2016.03.003.
[4] P. Scroll and D. For, “Earlier removal of concrete formwork,” Build. Res. Pract., vol. 1, no. 1, pp. 10–15, 1973, doi: 10.1080/09613217308550206.
[5] K. Jha, FORMWORK FOR CONCRETE STRUCTURES. 2012.
[6] M. K. Hurd, Formwoks for Concrete. 2005.
[7] K. Mosallam and W. F. Chen, “Design considerations for formwork in multistorey concrete buildings,” Eng. Struct., vol. 12, no. 3, pp. 163–172, 1990, doi: 10.1016/0141-0296(90)90003-B.
[8] P. Grundy and A. Kabaila, “Construction Loads on Slabs with Shored Formwork in Multistory Buildings,” ACI J. Proc., vol. 60, no. 12, pp. 1729–1738, 1963, doi: 10.14359/7911.
[9] X. L. Liu, H. M. Lee, and W. F. Chen, “Shoring and reshoring of high-rise buildings,” Concr. Int., vol. 11, no. 1, 1989.
[10] J. F. M. De Almeida Prado, M. R. Silva Corrêa, and M. A. Ramalho, “A new procedure for the analysis of construction loads in multistory reinforced concrete structures,” Struct. Des. Tall Spec. Build., vol. 12, no. 4, pp. 293–315, 2003, doi: 10.1002/tal.223.
[11] P. Sohoni, B. Mittal, V. A. Matsagar, and K. N. Jha, “Speedy Construction of Reinforced Cement Concrete Work in High-Rise Buildings by Optimizing Shoring and Reshoring Levels Using Genetic Algorithm,” Pract. Period. Struct. Des. Constr., vol. 25, no. 3, p. 05020002, 2020, doi: 10.1061/(asce)sc.1943-5576.0000483.
[12] P. Sohoni, A. Ghaffar, V. A. Matsagar, and K. N. Jha, “Optimization of Shoring/Reshoring Levels in High-Rise Building Construction,” Organ. Technol. Manag. Constr. an Int. J., vol. 10, no. 1, pp. 1803–1826, 2018, doi: 10.2478/otmcj-2018-0009.
[13] P. Sohoni and K. N. Jha, “Evaluating the factors for shore selection in multistorey building construction,” Int. J. Constr. Manag., vol. 0, no. 0, pp. 1–10, 2020, doi: 10.1080/15623599.2020.1762034.
[14] D. G. Proverbs, G. D. Holt, and P. O. Olomolaiye, “Factors in formwork selection: A comparative investigation,” Build. Res. Inf., vol. 27, no. 2, pp. 109–119, 1999, doi: 10.1080/096132199369570.
[15] R. Basu and K. N. Jha, “An AHP Based Model for the Selection of Horizontal Formwork Systems in Indian Residential Construction,” Int. J. Struct. Civ. Eng. Res., no. January, 2016, doi: 10.18178/ijscer.5.2.80-86.
[16] E. Martinez, I. Tommelein, and A. Alvear, “Formwork System Selection Using Choosing by Advantages,” Constr. Res. Congr. 2016 Old New Constr. Technol. Converg. Hist. San Juan - Proc. 2016 Constr. Res. Congr. CRC 2016, no. October 2017, pp. 1700–1709, 2016, doi: 10.1061/9780784479827.170.
[17] E. Elbeltagi, O. A. Hosny, A. Elhakeem, M. E. Abd-Elrazek, and A. Abdullah, “Selection of slab formwork system using fuzzy logic,” Constr. Manag. Econ., vol. 29, no. 7, pp. 659–670, 2011, doi: 10.1080/01446193.2011.590144.
[18] A. Krawczyńska-Piechna, “Comprehensive Approach to Efficient Planning of Formwork Utilization on the Construction Site,” Procedia Eng., vol. 182, pp. 366–372, 2017, doi: 10.1016/j.proeng.2017.03.114.
[19] A. Krawczyńska-Piechna, “Application of TOPSIS Method in Formwork Selection Problem,” Appl. Mech. Mater., vol. 797, no. April, pp. 101–107, 2015, doi: 10.4028/www.scientific.net/amm.797.101.
[20] S. K. Ghosh, “Construction loading in high-rise buildings,” Concr. Constr. Eng. Handbook, Second Ed., pp. 283–344, 2008, doi: 10.1201/9781420007657.ch8.
[21] H. G. Kwak and J. K. Kim, “Determination of efficient shoring system in RC frame structures,” Build. Environ., vol. 41, no. 12, pp. 1913–1923, 2006, doi: 10.1016/j.buildenv.2005.06.021.
[22] A. W. Beeby, “The forces in backprops during construction of flat slab structures,” Proc. Inst. Civ. Eng. Struct. Build., vol. 146, no. 3, pp. 307–317, 2001, doi: 10.1680/stbu.2001.146.3.307.
[23] P. F. Pallet, “Backpropping flat slabs,” www.temporaryworks.info Website, pp. 1–16, 2019, [Online]. Available: http://www.temporaryworks.info/PFP_136F_Backpropping_Flat_Slabs.pdf.
[24] S. George and W. Case, “C A S E S T U D I E S O N A P P Ly I N G B E S T P R Ac T I C E To I N - S I T U Co N C R E Te F R A M E D B U I L D I N G S St George Wharf Case Study Early age construction loading This Case Study looks at the experiences of applying new criteria for,” pp. 1–4.
[25] C. B. Project, “BEST PRACTICE GUIDES FOR IN-SITU CONCRETE FRAME BUILDINGS ... Early striking and improved backpropping for efficient flat slab construction,” Br. Cem. Assoc. behalf Proj. partners, pp. 1–4, 2001, [Online]. Available: www.bca.org.uk%0Awww.bca.org.uk%0Awww.bca.org.uk%0Awww.bca.org.uk%0Awww.bca.org.uk.
[26] B. Alamin, “Analysis of Construction Loads on Concrete Formwork,” 1999.
[27] Y. A. Alvarado, P. A. Calderón, I. Gasch, and J. M. Adam, “A numerical study into the evolution of loads on shores and slabs during construction of multistorey buildings. Comparison of partial striking with other techniques,” Eng. Struct., vol. 32, no. 10, pp. 3093– 3102, 2010, doi: 10.1016/j.engstruct.2010.05.028.
[28] Y. A. Alvarado et al., “An experimental study into the evolution of loads on shores and slabs during construction of multistory buildings using partial striking,” Eng. Struct., vol. 31, no. 9, pp. 2132–2140, 2009, doi: 10.1016/j.engstruct.2009.03.021.
[29] M. Buitrago, J. M. Adam, Y. A. Alvarado, P. A. Calderón, and I. Gasch, “Maximum loads on shores during the construction of buildings,” Proc. Inst. Civ. Eng. Struct. Build., vol. 169, no. 7, pp. 538–545, 2016, doi: 10.1680/jstbu.15.00089.
[30] X. Liu, W. Chen, and M. D. Bowman, “Construction Load Analysis for Concrete Structures,” J. Struct. Eng., vol. 111, no. 5, pp. 1019– 1036, May 1985, doi: 10.1061/(asce)0733-9445(1985)111:5(1019).
[31] P. C. Stivaros and G. T. Halvorsen, “Shoring/reshoring operations for multistory buildings,” ACI Struct. J., vol. 87, no. 5, pp. 589–596, 1990, doi: 10.14359/2669.
[32] P. Stivaros, “Shoring and Reshoring for Multistory Concrete Buildings,” Concr. Int., vol. 28, no. 2, pp. 33–38, 2006.
[33] M. Z. Duan and W. F. Chen, “Improved, simplified method for slab and shore load analysis during construction,” Project Report CESTR-95-21, p. 26, 1995.
[34] D. P. Fang, H. Y. Zhu, C. D. Geng, and X. La Liu, “On-site measurement of load distribution in reinforced concrete buildings during construction,” ACI Struct. J., vol. 98, no. 2, pp. 157–163, 2001, doi: 10.14359/10183.
[35] D. Fang, H. Xi, X. Wang, C. Zhang, and T. Zhao, “Load Distribution Assessment of Reinforced Concrete Buildings During Construction with Structural Characteristic Parameter Approach,” Tsinghua Sci. Technol., vol. 14, no. 6, pp. 746–755, 2009, doi: 10.1016/S1007-0214(09)70145-2.
[36] J. M. Adam, M. Buitrago, J. J. Moragues, and P. A. Calderón, “Limitations of Grundy and Kabaila’s Simplified Method and Its Repercussion on the Safety and Serviceability of Successively Shored Building Structures,” J. Perform. Constr. Facil., vol. 31, no. 5, p. 04017040, 2017, doi: 10.1061/(asce)cf.1943-5509.0001038.
[37] P. A. Calderón, Y. A. Alvarado, and J. M. Adam, “A new simplified procedure to estimate loads on slabs and shoring during the construction of multistorey buildings,” Eng. Struct., vol. 33, no. 5, pp. 1565–1575, 2011, doi: 10.1016/j.engstruct.2011.01.027.
[38] G. D. Redford, J. G. Rimmer, and D. Titherington, “Slope and Deflection of Beams,” in Mechanical Technology, 1969, pp. 308–335.
[39] M. Buitrago, Y. A. Alvarado, J. M. Adam, P. A. Calderón, I. Gasch, and J. J. Moragues, “Improving construction processes of concrete building structures using load limiters on shores,” Eng. Struct., vol. 100, pp. 104–115, 2015, doi: 10.1016/j.engstruct.2015.06.007.
[40] Y. A. Alvarado, M. Buitrago, I. Gasch, C. A. Prieto, and Y. A. Ardila, “Stage of construction: An essential consideration in designing reinforced concrete building structures,” Struct. Concr., vol. 19, no. 6, pp. 1551–1559, 2018, doi: 10.1002/suco.201700128.
[41] Y. A. Alvarado, M. Buitrago, I. Gasch, C. A. Prieto, and Y. A. Ardila, “Stage of construction: An essential consideration in designing reinforced concrete building structures,” Struct. Concr., vol. 19, no. 6, pp. 1551–1559, 2018, doi: 10.1002/suco.201700128.
[42] T. Lee, J. Lee, J. Kim, H. Choi, and D. E. Lee, “Effect of formwork removal time reduction on construction productivity improvement by mix design of early strength concrete,” Appl. Sci., vol. 10, no. 20, pp. 1–15, 2020, doi: 10.3390/app10207046.
[43] P. R. de Matos, R. D. Sakata, M. Foiato, W. L. Repette, and P. J. P. Gleize, “Workability maintenance of water-reducing admixtures in high-performance pastes produced with different types of Portland cement,” Rev. Mater., vol. 26, no. 1, 2021, doi: 10.1590/s1517- 707620210001.1225.
[44] Y. Liu and A. K. Schindler, “Finite-Element Modeling of Early-Age Concrete Stress Development,” J. Mater. Civ. Eng., vol. 32, no. 1, p. 04019338, 2020, doi: 10.1061/(asce)mt.1943-5533.0002988.
[45] J. Liu, C. Yu, X. Shu, Q. Ran, and Y. Yang, “Recent advance of chemical admixtures in concrete,” Cement and Concrete Research, vol. 124, no. July. p. 105834, Oct. 2019, doi: 10.1016/j.cemconres.2019.105834.
[46] T. Lee and J. Lee, “Setting time and compressive strength prediction model of concrete by nondestructive ultrasonic pulse velocity testing at early age,” Constr. Build. Mater., vol. 252, p. 119027, 2020, doi: 10.1016/j.conbuildmat.2020.119027.
[47] O. Obayes, E. Gad, T. Pokharel, J. Lee, and K. Abdouka, “Evaluation of Concrete Material Properties at Early Age,” CivilEng, vol. 1, no. 3, pp. 326–350, 2020, doi: 10.3390/civileng1030021.
[48] S. U. Khan, M. F. Nuruddin, T. Ayub, and N. Shafiq, “Effects of Different Mineral Admixtures on the Properties of Fresh Concrete,” vol. 2014, 2014.
[49] K. Poongodi, P. Murthi, P. O. Awoyera, and R. Gobinath, “Effect of mineral admixtures on early age properties of high performance concrete,” in IOP Conference Series: Materials Science and Engineering, 2019, vol. 561, no. 1, pp. 33–37, doi: 10.1088/1757- 899X/561/1/012067.
[50] X. Jin and Z. Li, “Effects of Mineral Admixture on Properties of Young Concrete,” J. Mater. Civ. Eng., vol. 15, no. 5, pp. 435–442, 2003, doi: 10.1061/(asce)0899-1561(2003)15:5(435).
[51] T. Lee, J. Lee, and Y. Kim, “Effects of admixtures and accelerators on the development of concrete strength for horizontal form removal upon curing at 10 °C,” Constr. Build. Mater., vol. 237, p. 117652, 2020, doi: 10.1016/j.conbuildmat.2019.117652.
[52] Shivram Bagade, Nagesh Puttaswamy, "Early High Strength Concrete Advantages and Challenges," March 2009. Available:https://www.nbmcw.com/product-technology/construction-chemicals-waterproofing/concrete-admixtures/early-highstrength-concrete-advantages-and-challenges.